P. 24-03 steps 1-4. Completed the roll bar bases and bolted into place on the fuselage. Then match drilled the holes through the roll bar into the bases, clecoeing after each drilled hole. Removed, deburred and primed, then reinstalled bases.
Wednesday, October 21, 2009
Subscribe to:
Post Comments (Atom)
Blog Archive
-
▼
2009
(89)
-
▼
October
(11)
- October 31, 2009: P. 27-05 Brake line installation
- October 13, 2009: Fuel Tank started!
- October 8, 2009: EAA Chapter 105 Visit
- September 12. 2009: P. 29-04 Upper Fuselage cont.
- September 7, 2009: P. 29-03, Fwd Upper Fuselage
- August 30, 2009: P. 27-02 Rudder Pedals
- August 13, 2009: P. 29-02 Upper Firewall Assembly
- July 18, 2009: P. 24-05 Baggage Bulkhead cont.
- July 15, 2009: P. 24-04, Baggage Bulkheads
- July 14, 2009: P. 24-03 roll bar continued
- July 12, 2009: P. 24-02 Roll bar frames
-
▼